I-10 Westbound Mixed flow lane addition |
Description: In Redlands and Yuciapa from west of Live Oak Canyon Road to east of Ford Street Overcrossing. Construct one westbound mixed flow lane.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Bernardino |
City | Redlands, Yucaipa |
Zip Code | 92373, 92374, 92399 |
Senate District |
31 |
Assembly District | 63, 65 |
Congressional District | 41 |
Caltrans District |
08 |
County/State Route | San Bernardino 10 |
Postmile Begin/End | 33.3 R 36.9 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 868 | 79744 |
Lane Miles Added (HOV) | 3.6 | |
Lane Miles Added (Mixed) | 3.6 | |
Peak Period Time Savings (minutes) | 69164 | 1134588 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
San Bernardino Associated Governments | Garry Cohoe | (909) 884-8276 | gcohoe@sanbag.ca.gov | |
Design (PS&E) Phase |
San Bernardino Associated Governments | Garry Cohoe | (909) 884-8276 | gcohoe@sanbag.ca.gov | |
Right of Way Phase |
San Bernardino Associated Governments | Garry Cohoe | (909) 884-8276 | gcohoe@sanbag.ca.gov | |
Construction Phase |
San Bernardino Associated Governments | Garry Cohoe | (909) 884-8276 | gcohoe@sanbag.ca.gov | |
Corridor System Management Plan |
Caltrans | John Pagano | (909) 383-6327 | john_pagano@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
CMIA |
$26,500 | $-12,426 | $14,074 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Local** |
$16,686 | $0 | $16,686 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $43,186 | $-12,426 | $30,760 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$0 | $0 | $0 | $130 | |||
Design(PS&E) |
$5,000 | $0 | $5,000 | $2,396 | |||
Right of Way |
$311 | $0 | $311 | $2 | |||
Construction |
$37,875 | $-12,426 | $25,449 | $19,752 | |||
Total* | $43,186 | $-12,426 | $30,760 | $22,281 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
07/01/2004 08/01/2007 |
|
07/01/2004 08/01/2007 |
100 | 07/01/2004 07/01/2007 |
0 1 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
08/01/2007 10/01/2009 |
|
08/01/2007 10/01/2009 |
100 | 08/01/2007 10/01/2009 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
08/01/2007 10/01/2009 |
|
08/01/2007 10/01/2009 |
100 | 08/01/2007 10/01/2009 |
0 0 |
|
Begin Construction Phase
End Construction Phase |
01/01/2010 06/01/2011 |
|
11/01/2010 05/01/2012 |
100 | 01/01/2011 08/01/2013 |
-2 -15 |
|
Begin Closeout Phase
End Closeout Phase |
07/01/2011 06/01/2012 |
|
06/01/2012 06/01/2013 |
0 | 02/01/2015 07/01/2015 |
-32 -25 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 06/01/2008 | 06/01/2008 | 95 | 07/01/2011 | -37 | ||
Implementation Date | 09/01/2008 | 09/01/2008 | 0 | 08/01/2011 | -35 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 868 | 79744 |
Lane Miles Added (HOV) | 3.6 | |
Lane Miles Added (Mixed) | 3.6 | |
Peak Period Time Savings (minutes) | 69164 | 1134588 |
Bond Funding Cost | |
---|---|
Adopted: |
$26,500,000 |
Current Approved: |
$14,074 |
Actual Expenditures: |
$12,481 |
Status as of December 31, 2023.